Current Projects

For the most up-to-date project information, view our most recent General Information report here. 

CURRENT PROJECTS

2021 CITYWIDE TRAFFIC SIGNAL EQUIPMENT IMPROVEMENTS
This project aims to upgrade signal equipment at 14 intersections within the City to decrease outages, update old technology, and increase safety. Not only will the traffic signals be upgraded, but reflective street signs and pedestrian  and bicycle buttons will be replaced. Staff worked together with Econolite System to complete the order for equipment and materials. Materials and equipment for traffic signals usually take several months to manufacturer. The recent pandemic increased shipment delays as well. The materials are expected to arrive within 6 to 8 weeks.

UPCOMING PROJECTS
2021-22 CITYWIDE STREET IMPROVEMENT PROJECT
This project consists of a grind and overlay and slurry seal treatment on several arterials, residential streets, and alleyways throughout the city. Staff is aiming for this project to be bid in July 2021 and to start construction in late August or early September 2021. This project is budgeted in the Measure M Fund, Gas Tax Fund, and RMRA Fund with no impact to the City's General Fund.

RECENTLY COMPLETED PROJECTS
FY 20/21 CONCRETE IMPROVEMENT PROJECT
After staff performed sidewalk inspections, 40 locations were determined to be potential tripping hazards by broken or raised sidewalks. The inspections took place in the neighborhood of Court Avenue, Jane Way, and Pine Tree Lane. Approximately 4,000 square feet of sidewalk was targeted for removal and replacement. The City of Stanton worked together with the Orange County Public Works department to improve these sidewalk locations. These improvements have helped the safety of pedestrians and accessibility of using the sidewalks. 

DEMOLITION & ABATEMENT AT TINA/PACIFIC
Due to fires and unsafe conditions, staff conducted and executed the demolition of the fourplex located at 8931 Pacific Avenue as well as 8881 Pacific Avenue. This project was funded with Housing Authority Funds with no impact to the City’s General Fund. The final construction cost for both projects totaled to $187,648.00.

2020 SEWER REPLACEMENT PROJECT

The City’s Sewer Master Plan identifies condition improvement recommendations and capacity improvement recommendations. The 2020 Sewer Replacement Project addressed deficiencies classified as “major”. The location was 300' north of Garden Grove Blvd. to Beach Blvd. and has experienced numerous sewer issues in the past. This project was funded from the Sewer Maintenance Fund with no impact to the City's General Fund. The final construction cost was $213,128.25.

FY 2020-21 CITYWIDE RESURFACING & SLURRY SEAL PROJECTS
These two projects addressed a total of 29 streets within the City that have had multiple failures in the past several years. The Resurfacing Project included complete reconstructions of streets that were in severe condition while the slurry seal was applied on top to others in order to help preserve and protect the underlying asphalt. Both projects were funded by the Measure M Fund, Gas Tax Fund, and the RMRA Fund with no impact to the City's General Fund. The final construction cost for the Resurfacing Project was $641,136.49 while the Slurry Seal Project was $474,307.89 for a total of $1,115,444.38 for both projects.